In brief: Construction drawing approval is the step that closes design and opens construction. Drawing review examines the content of a drawing; approval is the documented decision based on that review. In a well-run process, every step has a responsible person, an expected action, and a recorded result and time. In myPlan.cloud, an upload notifies the people involved, approval follows the order set in the approval workflow, the revision’s colour-coded status shows the decision, and every event is logged with a timestamp.
Drawing approval is a milestone in a construction project: from this point, what existed only on the drawing sheet starts to be built. That is why it matters who decides on the drawings, in what order and with what authority, and whether that decision can be traced later.
What is drawing approval for, and why does it matter?
The role of drawing approval in a construction project
Design also ties up resources, but its cost is orders of magnitude lower than the cost of construction. The same is true of changes: while a drawing is still only a drawing, a change costs an acceptable amount. During construction, every change becomes painfully expensive.
In other words, if something goes wrong at the drawing approval stage, it can turn into significant extra cost during construction.
Drawing review and drawing approval: what is the difference?
Review is the examination of a drawing’s content. Approval is the documented decision made as a result of that review.
Drawing review in the narrow sense is a professional task, carried out from a technical point of view by the reviewer responsible for the discipline concerned. Others can also have the right to review and approve, however: the client or its representative, for example, or even the financial manager responsible for the project budget. The approval process can therefore involve many participants and several levels. The aim is always the same: the drawings used for construction must be reviewed, accepted and clearly identifiable for everyone involved.
What happens without an approval system?
If a set of drawings has no approval system, a key piece of information is missing from each drawing: whether an authorised reviewer has accepted it. Nobody can say with certainty whether the drawing can be used on the project.
With a simple file system, this information exists somewhere too, in emails, spreadsheets or notes, but it is not clearly connected to the drawing. Acceptance is also only one question. The other is whether the drawing has a newer approved revision. Drawings stored in an ordinary file manager do not answer either question.
Who takes part in construction drawing approval?
| Participant | Role in the process | Approval rights? |
|---|---|---|
| Designers and discipline designers | Prepare the drawings, answer questions, make changes, upload new revisions | No |
| Technical reviewers and drawing checkers | Review the drawings technically and professionally, identify gaps and contradictions | Yes |
| Client, project manager and other authorised approvers | Check that project requirements are met, usually make the final decision | Yes |
Designers and discipline designers
They prepare the drawings, answer questions raised during review, and make changes where needed. They have no role in approval: they produce the drawings that are reviewed and approved, respond to change requests, and prepare new revisions.
Technical reviewers and drawing checkers
Their task is to review the drawings against technical and professional requirements. They apply general professional criteria (codes, standards, technical specifications) and check that the drawings meet the specific project goals and the client’s requirements. In doing so, they identify gaps and contradictions.
Client, project manager and authorised approvers
They usually represent a further approval level. They mainly check that project requirements are met, and they generally make the final decision.
How is the drawing approval process structured?
A well-designed drawing approval system consists of clear steps. Each step comes with three things:
- a defined responsible person,
- an expected action,
- a result and time that can be documented.
1. Uploading the drawing starts the process
The designer or the person responsible for the documentation uploads the drawing revision. This automatically starts the process: myPlan.cloud notifies everyone who has a task in that drawing folder, so they know that a new drawing has arrived. If the folder has an approval workflow, its participants are also notified about the approval task.
2. Reviewing and commenting on the drawings
The approvers review the drawings in the order defined in the workflow. The order is set in the approval schema, and myPlan.cloud is very flexible here: the process can be shaped as needed.
3. Recording comments and change requests
The reviewer has several tools for commenting on a drawing:
- A text comment on the revision. The comment can also be recorded as a drawing review. It then appears in a list where related progress can be followed, and the review gets a status (it can be marked as answered and as approved).
- Markup on the drawing preview. Drawing tools can highlight the requested changes and the problem areas.
Review information in one place: drawing markup, drawing review and revision status.
4. Deciding to approve or reject the drawing
Alongside text comments and markup, rejection of a revision is communicated clearly with a dedicated status button. Approval is simpler: comments and markup are possible here too, but setting the status to “Approved” is usually enough.
5. The result goes back to the designer
The authorised person either approves the drawing or sends it back for changes. In both cases, the change in the revision’s status shows the decision, and the designer is also notified by email. The drawing review attached to a rejection goes into a list, which shows the change request as an open task until the designer completes it, reports it as finished and uploads the new revision.
When the new revision is accepted, the reviewer sets the drawing review to “closed”, and the change request leaves the list of current drawing reviews.
It is essential that approval events are logged with their timestamps, because this can matter a great deal in a later dispute. myPlan.cloud logs the entire approval process and stores it in a searchable form.
How do you set up an approval hierarchy that fits your process?
The review and approval steps above are broadly the same across the construction industry. What varies greatly between companies and projects is
- the number of people assigned to review drawings,
- the number of levels in the process, in other words the decision hierarchy of the participants,
- the exact rights of the approvers.
In myPlan.cloud, all three can be configured freely.
Single-person approval
The simplest schema is single-person approval: one person decides whether to accept or reject the drawing, so there is no hierarchy and no order. The approver’s rights can still be configured.
Multi-level approval
myPlan.cloud also supports multi-level approval. A level can have several approvers, and you can set how many of them must approve for the level to be complete. Approvers on the next level are not called on, and are not notified, until the previous level is complete.
A multi-level approval schema: for each level, set how many approvals are needed to move on.
Approver rights
Each approver can have individual rights: for example, whether they can revoke a decision, or approve or reject in bulk. Bulk approval can be useful for a formal approver, for example.
Approver rights can be set for each person.
Which approval statuses does myPlan.cloud use?
Alongside markup, lists and notifications, perhaps the most important thing is that the status of a drawing in the approval process is clearly visible. The myPlan.cloud document management interface uses four statuses, each with its own colour:
| Colour | Status | What it means |
|---|---|---|
| Blue | Outside the approval workflow | A document without version control (contract, certificate, operating or maintenance instructions) with no approval status |
| Yellow | Awaiting approval | Uploaded to a folder with an approval workflow, but not yet approved or rejected |
| Green | Approved | The authorised people have accepted the revision |
| Red | Rejected | The revision has been sent back for changes |
Documents outside the approval workflow are marked blue.
The colour-coded status of each revision appears in every view, including the drawing register.
The drawing register shows the approval status of each revision.
How does myPlan.cloud support drawing approval?
The myPlan.cloud document management system supports drawing approval in six ways:
- Ease of use: approval takes a few clicks.
- Clarity: clear, colour-coded statuses in every view.
- Customisation: flexible approval schemas.
- Reliability: notifications are linked to the approval process.
- Functionality: a rich set of drawing review tools.
- Traceability: approval events can be retrieved later.
Frequently asked questions about drawing approval
What is the difference between drawing review and drawing approval?
Drawing review is the professional examination of a drawing’s content. Drawing approval is the documented decision, based on that review, on whether the drawing can be used.
Who takes part in drawing approval?
Designers prepare and, where needed, change the drawings, but they do not approve them. Drawing checkers, technical reviewers, the client, the project manager and other designated people can have approval rights.
How many approval levels can you set up in myPlan.cloud?
Anything from single-person approval to a multi-level schema. Each level can have several approvers, and you can set how many approvals the level needs.
When is the next approval level notified?
Only once the previous level’s approval is complete. Until then, approvers on the next level are not called on.
What happens to a rejected drawing?
The revision gets a red status, the designer receives an email, and the drawing review stays in the list as an open task until the designer uploads a new revision. Once the new revision is accepted, the reviewer closes the drawing review.
Can approval decisions be traced later?
Yes. myPlan.cloud logs the entire approval process with timestamps, which also helps in later disputes.
Related guides
After approval, what matters on site is that everyone works from the right revision. These guides can help:
- How to check that your team is using the latest drawing revision – QR code status checks and revision control.
- Construction task assignment and notifications – responsible groups and follow-up.
Set up your own approval workflow
You can also explore approval schemas, drawing review and status management on the construction document management page.
To discuss how multi-level drawing approval could fit your project, send an enquiry through the form. Our colleagues will get in touch.